Power & Heat

Kinyerezi Power Complex – Dar es Salam

Details
Client
Country
Tanzania
Location
Dar es Salaam
Period

Phase I:  150 MW SCGT Plant

Phase II:  240 MW CCPP – First combined cycle power plant in East Africa

Phase III:  185 MW SCGT Plant

Capacity: 150 / 240 / 185 MW
Configuration:
Phase I: 4 x LM 6000 (General Electric)
Phase II: 6 x H-25 (MHPS) & 2 x ST (KHI)
Phase III: 4 x LM 6000 (General Electric)

 

Owner’s Engineer

Services provided:

  • Project Management
  • Design Review and Approval
  • Factory Acceptance Tests Participation
  • Erection Supervision
  • Training to TANESCO Staff
  • Commissioning Supervision
  • Acceptance Testing Supervision
  • Defect Liability Period
Themen

More References

Mehr laden