Transmission and Distribution

Qatar Power Transmission System Expansion – Phase XIII Project

Details
Client
Country
Qatar
Location
Period

Capacity:

  • Construction of new substations
  • Substations
    3x 220 / 66 / 11kV
    18x 132 / 11  kV
    16x 66 / 11 kV
Services provided:

  • Extension and Modification of several Substations (including GIS)
  • Double circuit XLPE underground cables: 1x220kV, 20×132 kV, 8×66 kV
  • Cable connections within S/S area
  • Project Administration, Contract Management, Claim Management
  • Engineering Review
  • Factory Inspection and Acceptance Test
  • Supervision of Construction Works, Testing and Commissioning
  • Project Completion
Themen

More References

Mehr laden